Ireland · Legislation

Ireland CRU2025236

Ireland CRU2025236 has been enacted.

Published by the Commission for Regulation of Utilities in December 2025, this binding decision replaces the 2021 moratorium framework and requires new data centres above 10 MVA to provide on-site or proximate dispatchable generation matching their full grid import capacity, participate in the Single Electricity Market, and source 80% of annual electricity from additional Irish renewables within a six-year glide path. System Operators EirGrid and ESB Networks must assess each application against location constraints and publish a standardised connection process by 31 March 2026.

Official title

CRU Large Energy Users Connection Policy Decision (Data Centre Grid Connection Policy)

Bill details

Stage
Enacted
Policy area
Data Centers
Party origin
Bipartisan
Last updated

Focus areas

Topics this bill touches, used to group it with related legislation.

  • Grid Capacity

Primary sources

Read the bill text and legislative history at the source.

Ask about this bill

Put this record in front of EcoGPT and ask follow-up questions.

How would Ireland CRU2025236 change data-center development in Ireland?

Records current as of . The bill text and legislative history are linked below.